<< back

Foundation Works for Redevelopment
of Yau Tong Estate Phase 2

(Contract No. 34 of 1998)
油塘打樁第2期
(合約號1998年34號)

CLIENT
Hong Kong Housing Authority

ENGINEER
Hong Kong Housing Authority

CONTRACT VALUE
HK$30 million

CONSTRUCTION PERIOD
1998-1999

業主
香港房屋委員會

諮詢工程師
香港房屋委員會

合約額
3,000萬港元

工期
1998年至1999年

 

PROJECT HIGHLIGHTS
The project includes the design and execution of piling and pile caps to foundations and site works for the Redevelopment of Yau Tong Estate Phase 2 for the Hong Kong Housing Authority.

It consists of:
The design and execution of 54 nos of 2.3m diameter bored pile and pile caps to foundations to sustain the imposed loads for two 41-storey Harmony 1 (option 5) blocks.
The construction of a single-storey compound transformer and switch room and associated external works.
Modification of an existing platform.
 

  項目要點
本合約為香港房屋委員會油塘重建第2期房屋基礎工程的打樁和樁帽工程,包括設計和施工,計有:
- 設計並建造54個直徑2.3米鑽孔灌注樁,作為 兩座41層高和諧式住宅樓(方案5)的基礎。
-建造一座單層變電開關房及其室外工程。
-既有平臺改造。