Foundation for Tseung Kwan O Area 74 Phase 4
(Contract No. 58 of 1997)
將軍澳打樁第4期
(合約號1997年58號)

CLIENT
Hong Kong Housing Authority

ENGINEER
Hong Kong Housing Authority

CONTRACT VALUE
HK$93 million

CONSTRUCTION PERIOD
1998.1-1998.11

業主
香港房屋委員會

諮詢工程師
香港房屋委員會

合約額
9,300萬港元

工期
1998年1月至1998年11月

 

PROJECT HIGHLIGHTS
The project includes the design and execution of piling and pile caps to foundations and the execution of certain substructure works for the Hong Kong Housing Authority.

 It consists of:
  -The design and execution of 108 nos of 2.3m diameter bored pile and pile caps to foundations to sustain the imposed loads to six 41-storey Concord 1 (option 1) Blocks.
  -The construction of a transformer and switch room compound comprising single storey building and associated external works.

 

項目要點
本項目為設計弄建造基礎打樁、樁帽和些下部構造工程,包括:
 - 設計並建造108個直徑2.3米鉆孔灌注樁及樁帽,作為6座41層高住宅樓之基礎。
  - 建造一個單層變電開關房及室外工程。