Sing Woo Terrace Hawthorn Garden
跑馬地荷塘苑

CLIENT
Chanwell Investment Limited

ARCHITECT
Chan Kwok Wai & Associates Architects Engineers Ltd

CONTRACT VALUE
HK$15 million

CONSTRUCTION PERIOD
1992

業主
昌匯投資有限公司

則師
陳國威建築師事務所有限公司

合約額
1,500萬港元

工期
1992年

 

This is a renovation work for a 12-storey residential block with 2 levels of basement for carpark.

It consists of:
 * The replacement work of external facing tile & aluminium window, kitchen and bathroom tiling, sanitary fittings, etc
 * The renovation work of G/F entrance lift lobby.
 * The replacement of all plumbing and drainage pipework & gas installation.

 PROJECT HIGHLIGHTS
  This renovation work was for a 10-year old building and the developer was planned to re-sell in the real-estate market in a short period. So the contract period was vital and very tight.

 

本項目為一座12層住宅樓的翻新工程,地下兩層為停車場。

工程包括:
 
* 更換外牆貼面,鋁窗,廚房/衛生間貼面,衛生潔具,等等。
 
* 翻新地下入口電梯大堂。
 
* 更換全部上下水管及煤氣喉。

 項目要點
  發展商翻新這座10年樓齡的住宅樓,是為了短期內在物業市場上重新放售,因此工期非常緊。